Transaction is defined
The rate states exactly what completes a move or order line, including pickup and drop confirmation.
A useful warehouse truck RFQ states what the equipment carries, how often each route is demanded, where constraints occur, which control layer owns each decision and how performance will be accepted. This page reuses a compact compliance-style structure to capture those engineering facts—not sustainability slogans.
Use one row per operating case when loads or routes differ materially. Attach source files, timestamps and owners so changes can be traced during design review with Manitou.
| Input group | Minimum information | Why it changes the concept | Preferred evidence |
|---|---|---|---|
| Load unit | Length, width, height, mass, load center, underside, overhang, orientation and stability | Controls fork interface, residual capacity, pickup tolerance, braking and safe transfer | Dimensioned drawing, weight range, representative samples |
| Material flow | Origins, destinations, moves by interval, SKU/order profile, replenishment, peak duration and cutoff | Determines mission demand, travel, queueing, buffer occupancy and fleet quantity | Timestamped transaction extract and route matrix |
| Site geometry | Clear aisle width, turns, gradients, floor joints, doors, lifts, crossings, safety zones and charging areas | Defines feasible paths, speed restrictions, traffic rules and intervention access | Current CAD, measured survey, marked photographs |
| Control interfaces | WMS/WCS/WES/PLC ownership, messages, acknowledgements, timeouts, alarms and network policy | Prevents duplicated decisions, silent failures and unresolved exception states | Responsibility matrix, interface specification, sequence diagrams |
| Acceptance | Design and peak rates, transaction definition, availability boundary, test duration, fault cases and evidence owner | Turns commercial expectations into repeatable FAT and SAT decisions | Approved protocol, scenario data, result and deviation template |
The rate states exactly what completes a move or order line, including pickup and drop confirmation.
Demand identifies duration, recurrence, replenishment overlap and whether backlog is allowed.
Every station and lane has a capacity, blocking rule and response when full or unavailable.
Commands, data state, retries, alarms and manual decisions belong to named systems and teams.
Pedestrian crossings, restricted areas, maintenance access and intervention points appear on the layout.
Blocked routes, host silence, network loss, low energy, lost load and disabled stations have expected outcomes.
If the project cites ISO 3691, ISO 12100, ISO 13849-1 or a regional machinery regulation, specify whether each item is a design reference, product requirement, site integration obligation or requested third-party certificate. Do not use a framework name as a substitute for model-specific documentation. Manitou will not treat a logo row as acceptance evidence.
For brownfield deployments, include cutover zones, allowed downtime, rollback steps, inventory reconciliation and temporary manual flow. For expansion, include the next expected destinations, workload range, charging capacity and network growth so the initial phase does not create avoidable constraints.
Freeze the route map, truck configuration, interface version and test dataset before a run. Execute a named transaction mix for a stated duration, record completed and failed moves, queue time, buffer occupancy, energy state and recovery time, then repeat the same scenario after each material change. An example protocol requires a 120-minute nominal run followed by blocked-path, host-timeout and unavailable-station scenarios; the numbers are test conditions to approve, not Manitou performance claims.
When a site debates fixed automation against flexible robotics, keep the truck RFQ honest about duty cycle stability. If pallet move patterns are stable for years, deterministic dock-to-reserve truck paths may support higher design rates with simpler PLC handshakes. If SKU velocity and dock schedules change each season, document phased cutover, modular charging capacity and WCS ownership so a flexible fleet or mixed truck/AMR layout can expand without rewriting residual capacity assumptions after SAT.
Attach the route matrix, load evidence, site drawing, interface responsibility and draft acceptance scenarios. Mark unknowns clearly; they are inputs to resolve, not gaps to hide.
Submit project requirements